If six men can do a piece of work in 14 days. how many are needed to complete the project in 21 days

Respuesta :

Davidfridman
Davidfridman Davidfridman
  • 12-01-2018
you would need 9 poeple
Answer Link

Otras preguntas

A Mater Exam Q2 SA 1 4 Points What is the slope of a line that is perpendicular to the line f(x) = 2x + 6? Justify your answer by typing out your calculations o
Write an informative, research-based essay that explains what factors contributed to the escalation of the. I will mark brain list
A loan of $12000 was borrowed from the bank at 14% per annum calculate the interest on the loan at the end of the first year ?​
What are the risk factors and warning signs that made the atrocities of the Holocaust possible? What steps can be taken today to ensure that such inhumanities n
please help me with this math problem
4. How is the coordination number determined?
How did geography and migration affect the languages of Europe? Choose the languages that evolved directly from Latin
An eccentric chemistry professor (not mentioning any names) stops in every day and orders 250ml of Sumatran coffee at precisely 60.0°C. You then need to add eno
The simple interest earned for certain amount for 3 years at 5% is AED. 450. The amount invested is ________. I need the steps also
Having a mission is not important because you have to become whoever you need to in order for people to say "yes" to you. True False