In the EST graph above, what is the required time to complete task E?​

In the EST graph above what is the required time to complete task E class=

Respuesta :

sqdancefan
sqdancefan sqdancefan
  • 06-05-2022

Answer:

  8 time periods

Step-by-step explanation:

This Earliest Start Time graph shows task completion times on the arrow out of the bubble representing the task.

__

Task E completes in 8 time periods.

_____

Additional comment

The number in parentheses inside the bubble is the number of time periods before the task can be started, at the earliest. That number in the Finish bubble is the earliest the project can be completed.

Answer Link

Otras preguntas

Which of the following were new transport technologies after the Revolutionary War: More then one answer
which of the following crystals would be the best at insulating heat
On new islands formed by volcanic activity you will most likely find
How long did the nation follow Washington's lead on 2-term limit ?
Read the story again and find the past forms of these irregular verbs
20 pts pls help me i dont wanna fail dis ;C pls sav me In which choice is the ellipses used correctly to revise the following sentence from Madame Bovary? To sp
what would be an example of foreshadowing in a story about a magician who ends up going bad from to much power?
Which of the following determines the value of a piece of information? its applicability its popularity its origin
can someone help me and explain how u know ASAP PLZ
Could someone pleaseeeeee help me with my math! Thank you <3