if 40 workers can complete a piece of work in 15 days how many workers should be employed to complete the same work in 3 days​

Respuesta :

cdagone
cdagone cdagone
  • 07-10-2021
8 workers. 15/3=5. 40/5=8
Answer Link

Otras preguntas

What is the role of greenhouse gases in the atmosphere
Which form of RNA carries messages from the DNA to create proteins within the cell?
Help me pls carnt figure it out
Each package of muffins has 4 muffins. Sharon bought 12 muffins for $9.60. How much does one package of muffins cost? A. $0.80 B. $1.60 C. $3.20 D. $4.80
Which style of narration uses pronouns such as he, she, and they?
What part of North America did the French settle
Fie triunghiul ABC cu AB=AC, m(uFie triunghiul ABC cu AB=AC, m(unghiului B)=m(unghiului C)=38 grade perpendicularele in A pe AB respectiv pe AC intersecteaza BC
Describe the emotional journey Yosa Buson experiences in "The Badger" from New Flower Gathering. How does the haiku he writes afterwards capture the juxtaposi
Yoshi speaks with a loud volume and at a high pitch. Tara speaks quickly and softly. Who speaks articulately?
Compare transnet with a perfect competitor in terms of price, output and profit