It takes 5 hr for 2 bricklayers to build a park wall. How long would it take 8 bricklayers to complete the job?

Respuesta :

tyrapipkin00 tyrapipkin00
  • 08-07-2021
1 hour and 25 mins
It takes 1 hour and 25 mins to complete the 8 bricklayers job
Answer Link

Otras preguntas

state if the three sies lengths form a right triangle ; 10 cm , 49.5 cm , 50.5 cm
How did the monroe doctrine help America?
How does the volume of a prism change if each dimension of the prism is doubled?
state if the three sies lengths form a right triangle ; 10 cm , 49.5 cm , 50.5 cm
Find the unit rate. 6 ounces for 2.5 servings Help! Please
24 is 40% of what number?
The island of corsica which lies south of the ligurian sea is part of what country?
Two cars start from rest at a red stop light. When the light turns green, both cars accelerate forward. The blue car accelerates uniformly at a rate of 5.8 m/s2
How did the monroe doctrine help America?
Find the unit rate. $121.50 for working 18 hours