The work component at the lowest level of the WBS for which cost and duration can be estimated and managed is called the ______:

Respuesta :

dvynnjoku dvynnjoku
  • 07-01-2020

Answer:

The answer is Work Package.

Explanation:

Work Package is the work component at the lowest level of the work breakdown structure(WBS), for which cost and duration can be estimated and managed; beyond this level, further decomposition will not be done.

Work packages are the primary input to identify activities' process. They are planned by way of identifying activities under them.

Answer Link

Otras preguntas

please help if your able to (:
HELP!!!! IT'S DUE TONIGHT!!!!!!!!!!!!
23 PTS Points (−6, 3) and (−6, −3) on the coordinate grid below show the positions of two dogs at a park: (image attached) Which statement best describes the re
help me asap please i will give you a heart help me
5) What is the slope and the y-intercept of the line represented by the equation 4x + 3y - 12?
PLEASE ANSWER ASAP !!!
According to this information (keeping in mind that in 1824 a candidate had to win 131 electoral votes in order to win the election), which of these candidates
WHICH ONE !! A. 3 B. -3/4 C. -1 D. 3/4
Burke Enterprises sells toy flying saucers. The following information relates to toy sales during the month of June (the first month of operations) and to relat
Find: m∠1, m∠2, and m∠5 in degrees