76 persons can complete the job in 42 days-in how many days will 56 persons do the same job?

Respuesta :

PiaDeveau PiaDeveau
  • 17-11-2018

We are given that 76 persons can complete the job in 42 days.

We need to find the number of days will 56 persons do the same job.

Let us assume that in x number of days will 56 persons do the same job.

Number of days taken by 1 person to complete same work = 76 × 42 =3192 days.

56 person will take = [tex]\frac{3192 }{56}[/tex] = 57.

Therefore, 57 days will 56 persons do the same job.


Answer Link

Otras preguntas

Effective lessons planning helps early childhood teachers
what is the solution to the proportion? 8/16 = x/10
use transformation to solve this equation. -3 2/3x = 22
One half liter of lemonade is added to 3 liters of water. How many 1/3 liter servings of lemonade can be made?
Forme des phrases. Dix,Theo,ans,a les pupitres,il y a ,des ,sur,livres,des,cahiers,et,est,la,devant, de,classes,la,porte,Doudou. Ajutatima va rog!
American Revolution. True or false/History questions. Help? The Continental Army won the war mainly because they did mostly guerilla fighting. (True) or (False
Booker T. Washington believed that the best interests of African American people could be achieved through education and learning work related skills. He believ
Which statement about the physical properties of matter is true?
Plzzzz!! Help me !!!
What is the gravitational force excerted on an object called?