How long will it take 5 workers to complete a task, given that 8 workers can compete the same task in 10 days?

Respuesta :

purplefries
purplefries purplefries
  • 07-11-2018
8 workers can complete a task in 10 days, meaning the man-hours needed to this task is 80 man-hours.

Hence for 5 workers to complete the same task that require 80 man-hours, 80÷5= 16.

So, it will take 16 days for 5 workers to complete this task.
Answer Link

Otras preguntas

It says on image below I think
Triangle ABC has been reflected over the x-axis to create triangle A'B'C'. Which of the following statements is true? B'C' = 2 AB = 2 BC = 2 AC =2
thir Which section of the Declaration of Independence explains how the government is expected to treat its citizens? Help Resources A. Resolution of Independenc
Quiero denunciar el robo o plagio de una respuesta dada por mí, hace unos días. Un usuario (luciamirella15) borró mi nombre alegando que esa respuesta era incor
Help me pretty please
If the statement is true, write true. If the statement is false, change the underlined word or words to make the statement true. 3. ________________ If you inc
PLEASE HELP IM TIMED NO LINKS OR FILES THESE ARE NOT FREE POINTS WILL REPORT, ALSO I WILL GIVE BRAINLISET TO FIRST PERSON THAT ANSWER!
Solve please. 20 points.
What was the most important reason city residents lost their jobs and suffered from the Great Depression? Manufacturing slowed, so port cities shipped fewer go
WHAT IS THE SURFACE AREA OF THE SHAPE DUE BY 5:00 PM PLZ WITH WORK