chlolow8798 chlolow8798
  • 10-04-2024
  • Business
contestada

If our project is over budget but tasks are ahead of schedule, we may want to:

a. do nothing.
b. delay tasks on the critical path to reduce spending.
c. delay tasks that have float and are not on the critical path.
d. re-evaluate the viability of the project.

Respuesta :

Otras preguntas

Evaluate the expression when a=6 and y= -7
The distance covered by one step is 2.5 feet long. how many steps would the average person take to travel 50 feet
The points given in the table lie on a line.fund the slope of each line
Use elimination to solve this system of equations. 2r + 3s= 9 and 3r + 2s= 12
Mr.smog just bought a big-screen tv set. The screen is 48 in. wide and 27 in. high. Find the lenghth of its diagonal
Use elimination to solve this system of equations. 2r + 3s= 9 and 3r + 2s= 12
What joints do we use when lifting weights?
Explain why ionic compounds are formed when a metal bonds with a nonmetal but covalent compounds are formed when two nonmetals bond.
What is poem and a poetry
A line has a slope of -5 and passes through (1,-1).which is the equation of the line in point - slope form?