A project forecasting tool that represents the cost estimate of a project if it keeps to the same cost performance is called:


Estimate to Complete (ETC)


Variance at Completion (VAC)


Estimate at Completion (EAC)


Budget at Completion (BAC)

Respuesta :

Otras preguntas

Transform the equation x-3y=-15 to express it in slope-intercept form
Which country does coriander come from
What events were held at the globe theatre?
in tuck ever lasting why does winnie tell the constable she wasnt kidnapped?
find center,foci, and vertices of ellipse (x+3)^2/21+(y-5)^2/25=1
Using carbo loading to increase the store of glycogen seems to benefit only those athletes who engage in aerobic activities that are?
#1 What is the distance between the points (4, 7) and (4, –5)? A. 2 units B. 12 units C. 0 units D. 4 units #2 What is the distanc
Are women treated equally in America?
Five liters of gas at STP have a mass of 12.5 g. What is the molecular mass of the gas? a. 12.5 g/mol b. 25.0 g/mol c. 47.5 g/mol d. 56.0 g/mol e. 125 g/mol
#1 What is the value of the expression 7–3? Answers: A. –21 B. - 1/343 C.1/343 D. 343  #2What is the value of the expression 1/5^-5? Answe